I'm not sure if it was the plan all along, but it seems JMU's acquisition (over quite a few years) of homes in the Forest Hills area has allowed it to now (potentially) partner with the City and Commonwealth to straight out the end of University Boulevard that has a big (slow) loop as it approaches the Days Inn.
Here are the properties that JMU owns per my most recent accounting...
(click the map for a larger file)
Here's how it would go down...
- JMU would donate the needed land, valued at $3M.
- Engineers estimate the project will cost $9,140,000.
- The City will ask the Commonwealth for half of those funds -- $4,570,000.
- JMU would provide the remainder of the funds -- $4,570,000.
If this funding request is approved, construction on this realignment of University Boulevard would not be complete until December 2023.