Harrisonburg New City Hall

You can monitor progress on Harrisonburg's New City Hall (rendering above) online -- including viewing up to date construction photos.

Click here to view the project updates.

This project is scheduled to be complete in Fall 2015.  An update as of September 16th follows....
  • The structural steel is in the process of being erected and the new building is starting to take shape! Steel will continue going up throughout the week.
  • Plumbing and electrical work that will go under the concrete slab will begin at the end of September.
  • The first week of October, the concrete planks that will form the first floor and ceiling over the basement will arrive to be installed.
  • By mid October, the concrete slab for the basement will be poured.